Project Timeline
The key Project milestones are outlined below. These dates are approximate and may change as the Project moves forward.
This Project began in August 2026 and the design is expected to be completed in early 2028.
Design, tendering, and construction timelines depend on several factors. These include completion of the detail design and environmental assessment process, environmental review and approvals, any required permits or property requirements, utility coordination, and confirmation of funding and construction scheduling by MTO.
Summer
2026
Project Start
- Ontario Government Notice issued to announce the start of the study
- Project website launched
- Initial consultation with agencies, municipalities, utility companies, and nearby stakeholders
- Early field studies completed, such as natural environment baseline work and site review
Winter
2026/27
30% Design
- Preliminary intersection and lane configuration options developed
- Initial review of a possible driveway realignment near the intersection
- Ongoing consultation with agencies and stakeholders on the preliminary design
- Initial environmental findings prepared to help inform the design
Summer
2027
60% Design
- Preferred intersection design and lane arrangements refined
- Further development of construction staging, traffic management, and culvert replacement details
- Continued environmental and technical studies
- Design update shared with agencies, utility companies, and stakeholders
Fall
2027
90% Design
- Near-final design drawings and contract details completed
- Staging, access, and driveway realignment details finalized
- Transportation Environmental Study Report prepared
- Ongoing coordination with MTO and stakeholders on final design refinements
Winter
2027/28
Design and Environmental Assessment Completion
- Transportation Environmental Study Report completed and made available for a 30-day public review period
- Environmental commitments and steps to reduce impacts finalized
- Detail design and contract package completed for tender
- Final consultation summary completed and environmental clearance obtained
Spring
2028
Tender and Construction
- Contract package issued for tender
- Construction of the signalized intersection and related work anticipated to begin
- Construction staging, traffic management, and measures to reduce impacts implemented during construction
